• County wide roof distributed photovoltaic project [whole development process]
    • 发布时间:2022-3-15
    • Recently, the National Energy Administration officially issued the red headed document of the notice of the comprehensive Department of the National Energy Administration on submitting the pilot scheme of roof distributed photovoltaic in the whole county (city, district). The notice points out that the proportion of photovoltaic power generation that can be installed in the total roof area of Party and government organs shall not be less than 50%; The proportion of photovoltaic power generation that can be installed in the total roof area of public buildings such as schools, hospitals and village committees shall not be less than 40%; The proportion of photovoltaic power generation that can be installed in the total roof area of industrial and commercial plants shall not be less than 30%; The proportion of photovoltaic power generation that can be installed in the total roof area of rural residents shall not be less than 20%.

      图片1

      图片2

      图片3

      图片4

       

      Today, Beijing Multifit Electrical Technology Co., Ltd. will take you through the whole process of industrial and commercial photovoltaic development!

      1.Pre-development

      1-1 finding project resources

      1-2 preliminary communication with the owner

      1-3 preliminary data collection

      1-4 site survey

      1-5 technical scheme calculation

      1-6 determination of development intention

      1-7 signing relevant agreements

      1-1 finding project resources

      Photovoltaic project resources that can be developed

      Industrial Park / Development Zone

      sowntown

       

       

      Large industrial and mining enterprisesNational high-tech industrial park

      Local high-tech industrial parks

      logistics park

      Bonded Zone Economic development Zone

      Sewage treatment plant and other industrial plants

      hotels

      Office Building

      stadium

      airdrome

      railway station

      Large business center

      Supermarket and other commercial facilities

      Distributed pv development should be followed

      The principle of "adjusting measures to local conditions, clean and efficient, scattered layout, nearby use"

      1-2Preliminary communication

      Establish contact with the plant owners, interview with the plant situation, roof structure, electricity level and other basic issues, and determine the cooperation willingness and energy use demand.

      Through the data and satellite map, the following aspects are investigated to determine the feasibility of the project.

      Investigate the enterprise attributes (state-owned enterprises, listed enterprises, well-known foreign enterprises), whether the credit is good, operating conditions and income is stable, no bad record.

      Check whether the building property right is independent and clear (the original property ownership certificate, land certificate, construction planning permit), and whether the building property right is pledged.

      Investigate the roof structure (concrete, color steel tile), the service life and area of the roof (at least 20,000 square meters).

      Investigate the electricity characteristics, time-sharing electricity quantity, electricity price, voltage grade and transformer capacity.

      Check whether there is shelter or building planning around the building, whether there are gas or solid pollutants around the building.

      Investigate the owner's cooperation willingness, the preliminary communication cooperation mode (self-use, surplus power Internet).

      1-3Preliminary data collection list

      data name

      ask

      remark

       

       

       

      Credit review

      Business license of the building owners

      scanning copy

      Or photos

      As-built drawings CAD or scanned pieces

      photograph

      ✔ If the property ownership certificate is being handled, the housing management department needs to issue the receipt of the received materials, and the property ownership certificate must be obtained before the photovoltaic grid connection.

      ✔ If the building user and the property owner are the same, if the building user is only the lessee, does not have the property right, and is the future photovoltaic consumer, it needs to negotiate with the property owner to agree on the right to use the house.

      ✔ checks whether the building is mortgaged, and if mortgaged, you need to communicate with the mortgage unit.

       

      Proposed photovoltaic plant property ownership certificate

       

       

       

      Proposed photovoltaic plant land certificate

       

       

       

      Proposed photovoltaic plant construction planning permit

       

       

      Plant conditions

      General flat map of the factory

      photograph

      scanning copy

      Or photos

      As-built drawings CAD or scanned pieces

      ✔ plant layout, plant structure, electrical system, etc

      The ✔ provides the drawings for each plant building

      The ✔ calculates the roof load of each plant building

      ✔ predicts photovoltaic capacity, 0.6MW for 10,000 square meters of concrete roof and 10,000 square meters, and 1MW for 10,000 square meters of color steel tiles

       

      Plant structure diagram

       

       

       

      Building diagram of plant

       

       

       

      Plant area electrical system diagram

       

       

      Roof condition

      roof type

      photograph

      ✔ concrete roof / color steel tile

       

      Decoration situation in the workshop

      photograph

      ✔ specifies whether there is a suspended ceiling

       

      Roof life

       

      _

      The service life of ✔ concrete roof is long, which can generally guarantee the photovoltaic operation period of 25 years.

       

      Color steel tile laying time

       

      _

      The use of ✔ color steel tiles has waterproofing and maintenance issues, considering additional costs during the operating period.

       

      Color steel tile thickness

       

      _

      _

       

      Color steel tile type

      photograph

      ✔ determines type (T, angular, upright lock)

       

      Color steel tile color

      photograph

      _

      Power consumption

      Electricity bill of settlement

      scanning copy

      ✔'s recent electricity bill list for at least 12 consecutive months

       

      load curve

       

      ✔ reflects the power load and power time, so as to judge the proportion of photovoltaic self-use, the higher the proportion, the better the benefit.

      Production situation

      Construction time of plant

       

      _

      ✔ specific to year month

       

      Working hours for workers

       

      _

      The ✔ distinguishes between day and night work hours

       

      Holiday production situation

       

      _

      ✔ on weekends and holidays, to determine the annual production days

       

      Workshop production

       

      _

      ✔ defines the products and processes produced

      1-4Field survey on site

      After completing the preliminary evaluation of the project, the EPC team made a visit to the target enterprise.UAV aerial modeling was used to compare whether the architectural drawings were consistent with the actual situation, and the internal structure and roof of the plant were reviewed and photographed.

      微信图片_20220315161247

      Photovoltaic access system aspects

      other aspects 

      Brand and size of circuit breaker, brand and model of access line switch cabinet, reactive power compensation capacity and condition.

      How valuable is the type of items in the factory building.Is there a water source point to clean the photovoltaic system.

      1-5Technical scheme calculation

      Assess the overall operation situation of the enterprise, and determine the cooperation mode adopted.

      Focus of the project evaluation

      Building property rights

      And the right to use

      Building roof property right is clear

      Whether the ownership party and the use right party unanimously approve the project construction

      Can the Owner provide the corresponding convenient conditions for the project

      The ownership life and life of the building roof is more than 25 years

      building

      structural style

      Entrust the original roof design unit or a third party to calculate the roof load, and issue the certificate of meeting the photovoltaic installation conditions

      Whether the building structure can be strengthened can evaluate the difficulty and cost of reinforcement

      roofing

      Roof waterproof form and aging degree

      Assess the difficulty and cost of waterproof repair

      sthenosage

      Project cooperation mode

      Is the project economy feasible

      project investment

      Access distance of distributed PV

      Site construction is difficult and easily difficult

      1-6 Establish development intention

      Actively communicate with the enterprise owners, sign agreements, and enter the project filing stage.

      2On-grid acceptance

      2-1NDRC project filing

      County and district development and reform commission project record

      data name

      remark

       

       

      Distributed power supply project application form or project application Report

      Including the project implementation site, the source of investment funds, the simple explanation of the income, the owner situation, etc.

      Enterprise investment projects

      Company information, enterprise legal person business license, etc.

      Record form

      _

      investment in the fixed assets

      Roof (building) property certificate, owner authorized materials (such as roof lease contract), electricity sales agreement, etc.

      Project energy-saving registration form

      Roof plan, roof safety bearing capacity proof materials (issued by the qualified design unit), etc.

      2-2Power grid company access approval

      Get the county and district power grid company access approval

      data name

      remark

       

       

      The Distributed Power Supply Project Application Form

      Including the project implementation site, the source of investment funds, the simple explanation of the income, the owner situation, etc.

      Enterprise data

      ID card and photocopy of the operator, original power of attorney of legal person, business license of enterprise legal person, etc.

      Preliminary data of the power generation project

      Property ownership certificate or land certificate, roof lease agreement, electricity sales agreement, roof compression and roof area feasibility proof, fund certificate, etc.

      National Development and Reform Commission

      _

      User power grid related information and system access report

      _

      The power supply bureau accepts the application for grid connection

      Free access plan, out of the network opinion letter.

      List of main electrical equipment

      Including: photovoltaic modules, inverters, transformers and other equipment (grid-connected equipment selection should meet the national safety, energy saving, environmental protection requirements).

       3Design and construction

      After receiving the record and access approval, the EPC and the enterprise determined the design scheme, and the project entered and started smoothly.

      图片7

      scheme design

      Procurement bidding

       

       

      ✔Preparation of the feasibility study report

      ✔Preparation of project approval report or project application report

      Preliminary design of the ✔ Project

      ✔EPC Procurement Bidding for Project

      ✔ project supervision and procurement bidding

      ✔ main equipment and materials procurement bidding

      detail design

      Construction implementation

       

       

      ✔ field mapping, geological prospecting, demarcation, put forward design requirements

      ✔The access system report is prepared and the construction drawing and blueprint are reviewed

      ✔ professional drawings (structural, civil, electrical, etc.)

      ✔ Field Technical Exchange

      ✔The delivery line will be reviewed in the initial feasibility study, and will issue the power grid access opinions

      ✔ equipment procurement

      ✔ photovoltaic system construction work

      ✔ Electrical connection, protection and debugging, monitoring and installation of all equipment, etc

      ✔ unit project commissioning report / record power generation system before grid connection cannot trial operation

      ✔ Acceptance report / record of unit works before grid connection

      4On-grid acceptance

      Industrial and commercial photovoltaic projects are generally divided into three stages. The first stage is for project evaluation and contract signing, the second stage is for filing and access procedures, and the third stage is for construction and grid connection.

      图片8


      01.The project owner shall submit an application for grid connection acceptance and commissioning to the power grid company

      02.The power grid company accepts applications for grid connection acceptance and commissioning

      03.Sign the power purchase and sale contract and the grid connection dispatching agreement with the power grid

      04.Install the gateway electric energy metering device

      05.Complete the grid-connection acceptance and commissioning

      06.The project is connected to the grid